M2 Rack Mount Quick Reference Guide

M2 Rack Mount Quick Reference Guide

Equipment Overview

  1. UPS Battery

  2. Cellular router

  3. 4 or 8-port ATA(s)

  4. Cellular antenna and cable

  5. Power cable

  6. RJ11 ports

Rackmount with Numbers.png

Recommended tools and materials

All items below are required for MarketSpark technicians. Self-install customers may only need basic tools for mounting. Please use your judgment based on the scope of work and the install environment.

Tools

  • Laptop

  • Telephone butt set

  • Low voltage tone generator and probe

  • Label maker

  • Basic hand tool set (screwdrivers, etc.)

  • Screw gun/impact driver (if preferred)

 

Materials

  • Zip ties/wire consolidation accessories  

  • Cross-connect wiring

  • Cat 5/6 patch cables

  • Screw for use on walls and telco racks

  • RJ11 connectors

 

Install battery and power unit

Prior to mounting, locate the battery and UPS

Warning: Battery contacts are non-power limited. Shorting pins can cause sparks, arcing, or injury.

  1. Slide battery/UPS onto mount inside enclosure.

  2. Plug power cable and wiring harness into UPS.

  3. Ensure all connections between UPS and other devices are secure.

  4. Ensure battery/UPS assembly is secure.

  5. Plug device into unswitched wall outlet and ensure that the System Status LED is green.

  6. Swing L-bracket into place to properly secure battery, tightening screw.

Router light status

Confirm the following status lights based on the type of router provided.

1feda095-b623-4b31-a933-4f6f97dd03de.png
ee51db75-824d-4be6-b2f0-d2f86e592e97.png
1feda095-b623-4b31-a933-4f6f97dd03de.png
ee51db75-824d-4be6-b2f0-d2f86e592e97.png

InHand Router

PWR – red | SYS – yellow | NET – green

Cradlepoint Router

PWR icon – green | Modem icon – green
Signal icon – blue

Gateway light status

Confirm the following status lights based on the type of gateway provided.

b0f20d5e-2813-4cc2-aa13-06ebea066d8c.png
dc6ef39e-9c89-478b-bfbb-4e93a0c0fdaa.png
b0f20d5e-2813-4cc2-aa13-06ebea066d8c.png
dc6ef39e-9c89-478b-bfbb-4e93a0c0fdaa.png

Grandstream Gateway

PWR icon – blue | Globe icon – blue | #’d Voice Ports – lit as configured 

Patton Gateway

Power – green | VoIP – green | AUX 1 – green | ETH 0 – green

Signal and battery check

Use provided link to confirm signal and battery health, adjusting for signal if prompted. Ensure Battery Source is “AC” and State is “Good”.

  1. If signal or battery status is insufficient, call MarketSpark support at 1 (844) 335-5153.

power and signal cards.png

Perform test calls

  • Outbound: Use a butt set to call your cell phone from each RJ11 line. Answer call and speak. Confirm audio and caller ID before hanging up.

  • Inbound: Call each line  using your cell phone with the butt set attached to confirm inbound calls. Answer call and speak. Confirm audio before hanging up.

Do I need support?

If you encounter any issues with the MarketSpark equipment during install and testing, please call MarketSpark support at 1 (844) 335-5153.

Mount unit

The unit requires two rack units of vertical space and fits in a 19” computing rack. Use the included mounting screws to secure the chassis to the computing rack posts.

  1. Unplug the unit before mounting.

  2. Mount antenna at the top of computing rack or near an external wall for best signal.

  3. Avoid metal conduits and fluorescent light fixtures.

  4. Mount the antenna at least 2 feet away from coiled cabling, electrical equipment, or other antennas.

  5. Antenna cable must not be intertwined with other rack cables – power, Ethernet, etc..

  6. Run the antenna cable up the side of the rack opposite (1) the majority of other cables; if both sides (2) have coiled cabling, route the antenna cable up the center of the rack.

rack wiring.png

Locate POTS lines and perform patching (cutover), if in scope

Once the unit and antenna are mounted, powered on, and functioning correctly, begin identifying in-scope lines and proceed with patching (cutover).

rear.png
front.png
rear.png
front.png

Locate In-Scope Lines

  1. Identify phone numbers on the back of the MarketSpark chassis.

  2. Carefully remove each POTS line, labeling it with its number.

Patch Over to MarketSpark Lines

  1. Run a patch (cross-connect) from the MarketSpark RJ11 port to the device’s cross-connect point. Terminate as required.

  2. If surface mount jacks are in scope, install 
    and terminate at an approved location 
    for cutover.

Device testing (if applicable)

Test each device to confirm functionality on the new MarketSpark line. Include all necessary personnel in testing.

Common Examples

  1. Phone: Perform inbound and outbound calls

  2. Elevator: Verify call button behavior, 2-way audio, and proper line hangup (site contact)

  3. Fax: Send and receive test faxes (site contact)

  4. Life Safety Lines: No testing is required if terminating to surface mount jacks. For cutovers, the site contact or alarm vendor handles functional testing and CMS validation

Porting (if applicable)

After completing device testing on temporary MarketSpark numbers, call MarketSpark Support at 1 (844) 335-5153 to trigger the port request.

Checkout with support

Call MarketSpark Support at 1 (844) 335-5153 to complete a final validation check.

Clean up all debris and leave the area as you found it.